Goan Reporter News: A planned shutdown has been arranged at 220/110/33/11 KV Tivim Substation in North Goa on May 28, 2023 from 06.00 am to 12.00 pm for Pre monsoon maintenance affecting Bardez and Pernem Talukas.

0
535

The public of Bardez and Pernem Taluka are informed that a planned shutdown has been arranged at 220/110/33/11 KV Tivim Substation in North Goa on May 28, 2023, from 06.00 am to 12.00 pm to carry out pre monsoon maintenance of 220 KV and 110 KV equipments like Bus isolators, Transformer Isolators, breakers etc. and replacing of one section of the existing 110 KV Main bus with twin conductor. Therefore there will be no power supply to electricity consumers of the entire Bardez and Pernem Taluka.

Power supply will be made available to essential services like Assonora water works and District Hospital etc. as informed by the Department of Information and Publicity.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

CommentLuv badge